Gast Construction worked on the modifications for the Johnson Bridge starting in July 2014. These modifications included removing steel I-beams, two concrete piers, patching the slab at the piers, reinstalling one I-beam at a new location, and installing new steel. This project only took a month and was completed on time, making a safer bridge for walkers and bikers.